* The purpose of the project is to feed the central services complex (cooling building) from the site of the treatment plant in the Hadda area.
* Components of the project:
- Transportation lines: treated water line with a diameter of 1000mm of ductile iron pipe with a length of approximately 30 km.
- Lifting stations: The project contains three lifting stations with a capacity of 500 liters per second. The lifting stations contain a set of pumps, electrical rooms, and administrative buildings, in addition to a tank in lifting stations 2 and 3 to store water.